Campus Construction Update: June 14, 2019

Major landscaping includes:

Tile A

  • Finish backfill, additional install of granite and bituminous
  • North sidewalk extension to 10thStreet
  • Additional sodding along main sidewalk

Tile B

  • Continual watering

Tile D

  • Additional sod on north HSSC
  • Watering of sod and plantings

Tile E

  • Continue demo, grading and rock prep for new concrete sidewalks
  • Removal of old utilities at Highway 6, installation of new utilities and bedding rock
  • Install new traffic light sensors before granite crosswalk is installed