All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO – thermoplastic polyolefin (membrane); APC— Acoustical Panel Ceiling
HSSC: Major activity week of Oct. 8
- Equipment startup basement
- Testing/balancing
- Insulation – duct/pipe
- Drywall finish – north pavilion 3rd (project 99%)
- Paint – 2nd and 3rd floor north pavilion
- Ceiling grid – north pavilion as available
- Chilled beams – north pavilion 3rd completion
- Tile flooring – south pavilion 2nd and 3rd floor completion
- Tile flooring – south pavilion 1st floor
- GDC casework install – south pavilion
- Overhead MEP –3rd north pavilion
- Fin-tube – south pavilion
- PL-1 panels – south pavilion
- Lighting install – 2nd and 3rd north pavilion
- Interior glazing- north pavilion
- Atrium – APC-5 install
- Atrium – GFRG (gypsum/fiberglass) install complete
- Atrium – GFRG tape
- Atrium paint
- Restroom accessories and partitions south pavilion
- Punch begin – south pavilion (offices)
AFA: Major activity week of Oct. 8
This project will be completed mid-October, with move-in scheduled for Oct. 29 – Nov. 2. Remaining are final interior and exterior finishes, mechanical commissioning, and furniture installation.
College Landscape Project: Major activity week of Oct. 8
- Place bike shelter footing/paver pad/bike racks Noyce N/S sidewalk
- Subgrade prep HSSC north entrance paver area
- Underground rough in HSSC north
- Site walls HSSC north
- Start concrete restraining bands at coves
- Begin plantings AFA
- Install stone veneer at benches HSSC main plaza north
- Install pavers HSSC main plaza
- Prep paver area HSSC north
- Snowmelt prep/install HSSC north entrance