All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit.
HSSC: Major activity week of June 18
- Hang drywall – 2nd and 3rd floors, south pavilion
- Hang drywall – 1st floor west, south pavilion
- Drywall finish – 2nd and 3rd floors, south pavilion
- Paint – 2nd and 3rd floors, south pavilion
- Wall rough-in/backing/framing – 2nd and 3rd floors, north pavilion
- Overhead MEP – north pavilion
- Door frames – north pavilion (as needed)
- Floor box install – access floor locations
- Atrium – eyebrow soffit
- Atrium – high ceiling framing/drywall
- Rest rooms floor tile – south pavilion 2nd floor complete, begin 3rd floor
- Interior wall framing – 3rd floor, north pavilion/misc.
- Air barrier, waterproofing, atrium soffit (as needed)
- Brick veneer – north elevation (final)
- Copper metal panel field misc. trim complete
- Underground piping, north pavilion continuation
- Mass excavation/underground (landscaping)
- Hang drywall, north pavilion, 1st floor
- Ceiling grid, South Pavilion Resume
- Ceiling pads, south pavilion perimeter
- Interior glass, south pavilion
- Curtain wall trim, all elevations
- Exterior caulking, all elevations
- Interior punch window caulking, south pavilion
- Roof ladder completion, all roofs
AFA: Major activity week of June 18
- Re-start of trellis foundations
- Westside roof panels (high roof)
- Bridge soffits
- Finish curtain vestibules and doors
- Drywall grids 13-18, 2nd floor
- Tape and finish Room 102, 1st floor
- Prep walls for paint 1st floor grids 1-9
- Remove temp light pole at Macy House