All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit.
HSSC: Major activity week of June 11
- Hang drywall – 2nd and 3rd floor, south pavilion
- Drywall finish – 2nd and 3rd floor, south pavilion
- Paint – 2nd and 3rd floor, south pavilion
- Wall rough-in/backing/framing – 2nd and 3rd floor, north pavilion
- Overhead MEP – north pavilion
- Door Frames – north pavilion (as needed)
- Floor box install – access floor locations
- Atrium – roof drain extension eyebrow complete
- Atrium – eyebrow roofing
- Atrium – floor duct tie-ins
- Atrium – roofing completed less detail
- Rest rooms floor tile – south pavilion, 2nd floor
- Interior wall framing – 3rd floor, south and north pavilions/misc.
- Air barrier – waterproofing, atrium soffit (as needed)
- Brick veneer – north elevation (final)
- Copper metal panel field – north pavilion, south side completed
- Underground piping – north pavilion continuation
- Mass excavation/underground (landscaping)
- Hang drywall – north pavilion, 1st floor
AFA: Major activity week of June 11
- Drywall finish continues, 2nd floor
- All framing/rough-ins backing completed for northwest mechanical
- All trailers and storage trailers removed from alley
- Drywall finish, Rm 102
- Exterior cladding sub framing, start
- Complete west side grid 1-3 roof panels
- Complete stone work and demobilize