Campus Construction Update: Jan. 22–29, 2018

Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete.

HSSC: Major activity week of Jan. 22 through the week of Jan. 29:

  • Atrium skylight detail
  • Atrium hand rail tube steel
  • Interior framing, north pavilion 1st and 2nd floors
  • Exterior wall framing/sheathing, north pavilion
  • Exterior framing/sheathing, south elevation, south pavilion
  • Frames punch windows, south elevation
  • Frames windows north pavilion, south elevation
  • Window blocking, north pavilion
  • Window backing, north pavilion
  • Wall backing/blocking, south pavilion
  • Air barrier detail north pavilion/south and roof
  • Air barrier detail/spray (all available locations)
  • 2nd south MEP in-wall
  • Electrical/plumbing OH, north pavilion 1st and 2nd floors
  • Electrical/plumbing OH, south pavilion 2nd floor
  • Basement MEP continuation
  • Temporary weather protection
  • Roofing, north pavilion
  • Interior wall backing, south pavilion 1st and 2nd floors
  • Masonry, east elevation, south pavilion/air barrier detail
  • Skylight glass install south pavilion
  • Floor densifier install south pavilion
  • Completion of SOD and misc. interior concrete 99%
  • Roof prep/install south lower C
  • Framing completion lower roof C perimeter
  • Continuation steel detail work
  • Completion atrium arch

AFA: Major activity week of Jan. 22 through the week of Jan. 29:

  • Sheet 2nd floor west exterior
  • Sheet south elevation
  • Roof framing low roof west
  • Set scaffold and enclose for fireplace masonry
  • Lay bottom course for hearth
  • Receive and set roof trusses
  • Build fire box for fireplace
  • Receive and set AHU south mechanical room
  • Store and protect north AHU
  • North wall elevation exterior framing
  • Pour stair #2 treads