Campus Construction Update: Jan. 15–22, 2018

Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; any reference to “pour” refers to pouring concrete.

HSSC: Major activity week of Jan. 15 through the week of Jan. 22:

  • Atrium skylight detail
  • Atrium hand rail tube steel
  • Atrium roof decking
  • Carnegie tie-in structural bearing
  • Carnegie interior structural clips
  • Interior framing, north pavilion 1st and 2nd floors
  • Exterior wall framing/sheathing, north pavilion
  • Exterior framing/sheathing, south elevation, south pavilion
  • Frames/windows, north pavilion, south elevation
  • Window blocking, north pavilion
  • Window backing, north pavilion
  • Door frames, north and south pavilions
  • Wall backing/blocking
  • Air barrier detail (all locations available)
  • Interior wall rough-ins MEP south pavilion
  • Electrical/plumbing OH, south pavilion 1st and 2nd floors
  • Basement MEP continuation
  • Temporary weather protection
  • Roofing, north pavilion
  • Interior wall backing, south pavilion 1st and 2nd floors
  • Masonry, SE and east elevations, south pavilion
  • Lower C south pavilion roof blocking and framing

AFA: Major activity week of Jan. 15 through the week of Jan. 22:

  • Frame 2nd floor north wall exterior
  • Roof framing, low roof west
  • Set scaffold and enclose for fireplace masonry
  • Start south exterior wall framing
  • Pour stair #2 (south stairs)
  • Roof framing, low roof north
  • Start west (north half) exterior wall framing
  • Set east vestibule structural steel
  • Pour east vestibule isolation joints following steel erection

 

 