Campus Construction Update: Feb. 5–12, 2018

Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing.

All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete.

HSSC: Major activity week of Feb. 5 through the week of Feb. 12

  • Atrium/skylight detail
  • Interior framing, north pavilion 1st and 2nd floors
  • Exterior wall framing/sheathing north pavilion
  • Frames punch windows north elevation, north pavilion
  • Air barrier detail/spray (all available locations)
  • Roofing north pavilion
  • 3rd floor north pavilion fireproofing
  • Electrical/plumbing OH north Pavilion 1st and 2nd floors
  • Atrium facia
  • Atrium decking complete – (facia perimeter)
  • Basement MEP continuation
  • weather protection
  • Window backing/blocking
  • Masonry, east elevation, south pavilion
  • Parapet blocking north/south pavilion
  • Lower roof south pavilion air barrier
  • Lower roof south pavilion roofing
  • 3rd floor priority walls, framing, south pavilion
  • South pavilion arch stairs 001
  • Continuation steel detail work (south/north/atrium)
  • Glass punch windows, north pavilion, north elevation
  • Wall backing/blocking south pavilion/north pavilion
  • Clerestory frames delivered/install begin
  • 3rd floor MEP OH south pavilion
  • 3rd floor south pavilion framing
  • Electrical/plumbing OH, south pavilion 2nd floor
  • Roofing, south pavilion lower C
  • Prep for lower C roof fireproofing
  • Atrium stage install
  • South pavilion stairs complete 001
  • South pavilion drywall start
  • Framing completion lower roof C perimeter
  • Completion atrium arch

AFA: Major activity week of Feb. 5 through the week of Feb. 12

  • Set roof truss, north section
  • Complete detailing, south roof truss
  • Frame interior priority walls for MEPs
  • Roof framing, low roof west
  • Build fireplace box
  • Pour stair #2 treads
  • Roof blocking, south section
  • Prep steel for waiting room area (exposed beams)
  • Install roof steel decking, south area
  • Ductwork overhead, 1st floor
  • Roof decking
  • Wood blocking, south
  • Fireplace CMU
  • Detailing, north roof truss
  • Frame north exterior walls