Campus Construction Update: Feb. 19–26, 2018

construction site in snow
North pavilion – north elevation

Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete.

HSSC: Major activity week of Feb. 19 through the week of Feb. 26           

  • Interior framing, north pavilion, all floors
  • Exterior wall framing, west atrium
  • Segmented wall window clips
  • Atrium clerestory window frame complete and glass install
  • Roofing lower south pavilion “green”
  • Door frames, backing/blocking, south pavilion 2nd and north 3rd floors
  • Drywall 1st floor, south pavilion
  • Wall backing/blocking, south pavilion, 3rd floor
  • Frames punch windows north elevation, complete
  • Air barrier detail/spray
  • Interior wall backing, south pavilion 2nd and 3rd floors
  • 3rd floor south pavilion framing
  • Atrium facia, complete
  • Basement MEP continuation
  • Masonry, east elevation, south pavilion
  • Parapet blocking north/south pavilion
  • 3rd floor priority walls, framing/drywall, north pavilion
  • South pavilion arch stairs 001
  • Continuation steel detail work
  • 3rd floor MEP OH south pavilion
  • Electrical/plumbing OH, north and south pavilion 2nd and 3rd floors
  • Masonry east elevation, south pavilion
  • Roofing, north pavilion
  • Atrium soffit decking
  • Segmented curtain wall install
  • South pavilion curtain wall
  • Halo light gauge framing
  • South pavilion drywall 2nd floor
  • South pavilion 1st floor tape

AFA: Major activity week of Feb. 19 through the week of Feb. 26

  • Sheet north exterior walls
  • Receive roof insulation
  • Pour isolation joints at vestibules
  • Pour stair #2 treads
  • Mockup stone arrives
  • Mockup window arrives
  • Metal roof decking, complete
  • Wood blocking at fascia
  • Waiting room steel, erect
  • Overhead ductwork at 1st floor, complete
  • Priority walls on 2nd floor framing
  • Gable wall framing, complete
  • Start of spray on vapor barrier
  • Start plumbing piping racks overhead
  • Roof decking
  • Wood blocking, south
  • Fireplace fire box
  • Fireplace CMU complete
  • Frame north wall low roof joist