Campus Construction Update: Feb. 12–19, 2018

Main power service shut down/re-energize on Saturday, February 17 will affect existing Carnegie and ARH from 6 a.m. to 12 noon. Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete.

HSSC: Major activity week of Feb. 12 through the week of Feb. 19    

  • Interior framing, north pavilion, all floors
  • Exterior wall framing, west atrium
  • Atrium handrail, structural
  • Atrium clerestory window frames (dry set)
  • Roofing lower south pavilion “green”
  • Door frames/backing, south pavilion, all levels
  • Drywall 1st floor, south pavilion
  • Wall backing/blocking, south pavilion
  • Frames punch windows north elevation, north pavilion
  • Air barrier detail/spray
  • Interior wall backing, south pavilion 1st and 2nd floors
  • 3rd floor south pavilion framing
  • Atrium facia
  • Basement MEP continuation
  • Window backing/blocking
  • Masonry, east elevation, south pavilion
  • Parapet blocking north/south pavilion
  • 3rd floor priority walls, framing, south pavilion
  • South pavilion arch stairs 001
  • Continuation steel detail work
  • Glass punch windows, north pavilion, north elevation
  • 3rd floor MEP OH south pavilion
  • Electrical/plumbing OH, north and south pavilion 3rd floor
  • Roofing, south pavilion lower C “green”
  • South pavilion stairs
  • Masonry east elevation, south pavilion

AFA: Major activity week of Feb. 12 through the week of Feb. 19:

  • Set roof truss, north section
  • Frame interior priority walls 2nd floor for MEPs
  • Roof blocking, south section
  • Prep steel for waiting room area (exposed beams)
  • Install roof steel decking, south area
  • Install roof decking, south area
  • Install low pressure duct work, first floor
  • Start plumbing piping rough-in
  • Roof decking
  • Wood blocking, south
  • Fireplace CMU
  • Detailing, north roof truss
  • Frame north exterior walls