All major work activities for the Humanities and Social Studies Center (HSSC) and campus landscaping are included below.
Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO – thermoplastic polyolefin (membrane); APC — Acoustical Panel Ceiling; GDC — glass display cabinet; CRFRG — columns; FA — fire alarm; TCO — temporary certificate of occupancy
HSSC: Major Activity Week of Dec. 17
• Punch All Areas (Preliminary and Formal)
• Testing/Balancing
• Paint-Punch North Pavilion/Punch South Pavilion
• LVT-South Pavilion/North Pavilion Complete
• All Marker Boards Completed-North and South
• Wood Floor North Pavilion/Carpet Inserts
• Ceiling Grid – Remaining 1170
• Lighting and FA Devices Complete
• Tile Flooring – North Pavilion Complete
• North Pavilion Door & Hardware 90 %Complete
• GDC Cabinet Install-North Pavilion Started
• Carpet Install – North Pavilion Complete
• Slatwall Substrate – Atrium Complete
• Bridge Baswa/Plaster Repairs – Atrium Complete
• GFRG Paint – Atrium Complete
• Glass Railing Install Complete (Only Glass)
• Paint Structural – Atrium Complete
• Ceiling Pads North and South Pavilion Complete
• Final Clean
• ST10 Monument Stairs Complete
• Fire Curtain Testing
• Smoke Evac Testing
• FA Testing
• Wattstopper Programming
• GTB Delivery North Pavilion
• All Systems Complete Testing
HSSC: Major Activity Week of Dec. 24
• Testing/Balancing
• Punch – All Areas
• Final Clean
• Corner Guard Install (TBD)
• North Pavilion Door & Hardware Completed
• South Pavilion Misc. Door and Hardware
• Slatwall Substrate – Misc
• Tile Install – Atrium
• Bridge Railing System Complete
• Fire Curtain Testing
• Fire Alarm Testing
• Final Inspection City & State
• TCO!!!