All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO –thermoplastic polyolefin (membrane)
HSSC: Major activity week of Aug. 20
- Basement MEP startup preparation
- Insulation – duct/pipe north pavilion
- Hang drywall – 3rd floor north pavilion/skylight south pavilion
- Drywall finish – north pavilion 2nd and 3rd/skylight south pavilion
- Paint – 2nd floor north pavilion
- Ceiling pads – south pavilion 3rd floor
- Ceiling grid – north pavilion 1st floor
- Ceiling pads – north pavilion 1st floor
- Chilled Beams – north pavilion 2nd and 3rd floors
- Carpet/LVT – south pavilion 3rd floor
- Carpet/LVT – north pavilion 1st floor
- Overhead MEP – 3rd north pavilion
- Spray foam – atrium high roof sheathing (as needed)
- Atrium bridge ceiling framing
- Restroom floor tile – north pavilion 1st and 2nd floor
- Overhead MEP – 2nd/3rd floors north pavilion
- Stone vestibules – north-south pavilion
- Millwork south pavilion
- Vestibule doors/frames
AFA: Major activity week of Aug. 20
- Install ceiling tile, 2nd floor
- Install light fixtures, 2nd floor
- Install grilles, 2nd floor
- Drop fire protection heads, 2nd floor
- Drop fire protection heads, 1st floor
- Paint door frames, 2nd floor
- Install side light glass in HM frames, 2nd floor
- Swinging wood doors, 2nd floor
- Install Swiss pearl system
- Install copper roof panels
- Finish welding/decking/detailing of trellis structure
- Install plumbing fixtures, 2nd floor
College Landscape Project: Major activity week of Aug. 20
- Bench footings HSSC north side main plaza
- Subgrade prep, HSSC main plaza
- Gas line, AFA north
- Sidewalk, AFA north
- Concrete paving, AFA parking lot
- Electrical rough-in, HSSC main plaza
- Install bioswale north of HSSC