All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit.
HSSC: Major activity week of April 16
- Basement MEP insulation/steam
- Hang drywall – 2nd floor, south pavilion
- Drywall finish – 1st and 2nd floors, south pavilion
- Paint – south pavilion, 1st floor
- Wall rough-in/backing/framing, 3rd floor south
- Pavilion, 1st floor A
- Overhead MEP – 2nd and 3rd floors, south and north pavilions
- Door frames – north pavilion
- Atrium – fire dampers
- Atrium – roof drains
- Interior wall framing – 3rd floor, south and north pavilions
- Roofing – atrium
- Curtainwall – atrium east elevation
- Brick veneer – south pavilion, northeast elevation
- Steel detailing – misc. steel
- Freight elevator – completion
- Tower crane demobilize (Friday-Sunday)
- Metal panel field – south pavilion
AFA: Major activity week of April 16
- Complete 1st floor wall rough-ins
- Window install continues 2nd floor
- 2nd floor restroom wall rough-ins
- 2nd floor wall framing completed
- Wall backing on 1st floor completed
- Frame soffits in waiting room
- Waiting room overhead rough-ins
- HVAC lines to AFA continue at south entry point
- Receive remaining balance of res windows
- Backfill stoops