Campus Construction Update: Sept. 10–16

All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO – thermoplastic polyolefin (membrane); APC— Acoustical Panel Ceiling

HSSC: Major activity week of Sept. 10

  • Basement MEP startups
  • Insulation – duct/pipe continuation
  • Hang drywall – 3rd floor north pavilion
  • Drywall finish – north pavilion 2nd and 3rd
  • Paint – 2nd floor north pavilion
  • Ceiling grid – north pavilion 2nd floor
  • Chilled beams – north pavilion 2nd and 3rd
  • Flooring – south pavilion 3rd floor
  • Lab casework install – south pavilion
  • Overhead MEP – 3rd north pavilion
  • Atrium bridge ceiling MEP
  • Atrium bridge – plaster
  • Restroom floor tile – 2nd and 3rd floor north pavilion
  • Overhead MEP – 2nd and 3rd north pavilion
  • Doors and hardware – south pavilion 1st and 2nd floors
  • Framing/sheetrock 99% completed – south pavilion
  • Tape fire curtains – south pavilion
  • Lighting install – south pavilion 3rd, 1st north pavilion
  • Stoops footings/pads – south pavilion x 2 (weather permitting)
  • Window stool trim – south pavilion
  • Interior glazing – south and north pavilion
  • Waldinger Utilities – (weather permitting)
  • Exterior east elevation eyebrow APC-4-atrium
  • Interior APC-5-atrium (main grid)
  • Turn permanent lights and power on – south pavilion

AFA: Major activity week of Sept. 10

  • Wood door and hardware install on 1st floor
  • Paint 1st floor/bridge railing
  • Ceiling tile and grid install on 1st floor
  • Blocking and stud framing on the trellis
  • Install of the Swiss pearl system
  • Detail copper roof/soffit and fascia/gutters
  • Granite base install
  • TPO roofing install on trellis
  • Shade install
  • General clean
  • Install backsplash above millwork
  • Install atrium ceiling grid
  • Install light fixtures where available
  • Millwork install
  • Countertop and sill install

College Landscape Project: Major activity week of Sept. 10

  • Install light poles AFA east, south, noyce n/s sidewalk
  • Install cove stone north 1/3 HSSC south courtyard
  • Subgrade prep HSSC main plaza
  • Underground rough in HSSC main plaza
  • Fine grade AFA south
  • Subgrade prep HSSC south courtyard
  • Demo alley/grade and prep AFA
  • Install slit drains HSSC main plaza
  • Install cantenary light pole bases HSSC main plaza
  • Place alley paving AFA