All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO – thermoplastic polyolefin (membrane); APC— Acoustical Panel Ceiling

HSSC: Major activity week of Oct. 8

  • Equipment startup basement
  • Testing/balancing
  • Insulation – duct/pipe
  • Drywall finish – north pavilion 3rd (project 99%)
  • Paint – 2nd and 3rd floor north pavilion
  • Ceiling grid – north pavilion as available
  • Chilled beams – north pavilion 3rd completion
  • Tile flooring – south pavilion 2nd and 3rd floor completion
  • Tile flooring – south pavilion 1st floor
  • GDC casework install – south pavilion
  • Overhead MEP –3rd north pavilion
  • Fin-tube – south pavilion
  • PL-1 panels – south pavilion
  • Lighting install – 2nd and 3rd north pavilion
  • Interior glazing- north pavilion
  • Atrium – APC-5 install
  • Atrium – GFRG (gypsum/fiberglass) install complete
  • Atrium – GFRG tape
  • Atrium paint
  • Restroom accessories and partitions south pavilion
  • Punch begin – south pavilion (offices)

AFA: Major activity week of Oct. 8

This project will be completed mid-October, with move-in scheduled for Oct. 29 – Nov. 2.  Remaining are final interior and exterior finishes, mechanical commissioning, and furniture installation.

College Landscape Project: Major activity week of Oct. 8

  • Place bike shelter footing/paver pad/bike racks Noyce N/S sidewalk
  • Subgrade prep HSSC north entrance paver area
  • Underground rough in HSSC north
  • Site walls HSSC north
  • Start concrete restraining bands at coves
  • Begin plantings AFA
  • Install stone veneer at benches HSSC main plaza north
  • Install pavers HSSC main plaza
  • Prep paver area HSSC north
  • Snowmelt prep/install HSSC north entrance