Campus Construction Update: Oct. 1-7

All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO – thermoplastic polyolefin (membrane); APC— Acoustical Panel Ceiling

HSSC: Major activity week of Oct. 1

  • AHU2 Startups
  • Insulation- Duct / Pipe
  • Drywall – 3rd Floor North Pavilion
  • Drywall finish – North Pavilion 3rd
  • Paint-2nd Floor North Pavilion
  • Ceiling Grid – North Pavilion
  • Chilled Beams – North Pavilion 3rd
  • Tile Flooring – South Pavilion 2nd and 3rd Floor
  • GDC Casework Install – South Pavilion
  • Overhead MEP – 2nd/3rd North Pavilion
  • Doors and Hardware – Basement
  • Lighting Install –1st and 2nd North Pavilion
  • Stoops Footings / Pads- South Pavilion x 2
  • Window Stool Trim – South Pavilion
  • Interior Glazing – South and North Pavilion
  • Atrium- APC-5
  • Atrium- L29 Light Fixture Installer
  • Atrium- GFRG Erection Completion
  • Atrium Bridge – Plaster

AFA: Major activity week of Oct. 1

This project will be completed mid-October, with move-in scheduled for Oct. 29 – Nov. 2.  Remaining are final interior and exterior finishes, mechanical commissioning, and furniture installation. 

College Landscape Project: Major activity week of Oct. 1

  • Fine grading AFA
  • Dig bioswales HSSC North
  • Install light poles AFA
  • Install pole bases AFA North and West
  • Snowmelt prep/install HSSC Main Plaza
  • Place concrete pavers base HSSC Main Plaza