Campus Construction Update: May 7–13

Please note: During the next 4-6 weeks, the HSSC main entrance on the north side (#1) will be closed due to plumbing underground, and the south HSSC gate (#3) will be the “new” main entry. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit.

HSSC: Major activity week of May 7

  • Basement equipment install MEP
  • Hang drywall – 2nd floor south pavilion/stairwells
  • Drywall finish – 1st and 2nd floors, south pavilion
  • Paint – south pavilion, 1st floor
  • Ceiling Grid – south pavilion, 1st floor
  • Wall rough-in/backing/framing – 1st floor, north pavilion
  • Overhead MEP – north pavilion
  • Door Frames – north pavilion
  • Atrium – scaffold extension
  • Atrium – roof drains
  • Interior wall framing – 3rd floor, south and north pavilions
  • Framing – atrium roof soffit
  • Air barrier – waterproofing, atrium soffit
  • Curtainwall – atrium, east elevation glass
  • Curtainwall – NW north pavilion glass
  • Brick veneer – NE elevation, north pavilion, 95% complete
  • Steel detailing – south pavilion/stairs
  • Elevator – E301 south pavilion
  • Metal panel field – south pavilion, south side completed
  • Underground piping – north pavilion, north side

AFA: Major activity week of May 7

  • Continue stone wainscot
  • Start of roof panels
  • Complete soffit foam, northeast
  • Complete soffit blocking, northeast
  • Drywall continues, 1st floor
  • MEP rough-in inspection, 2nd floor, grids 1-9
  • Stock drywall, 2nd floor