Campus Construction Update: Feb. 26–March 5

HSSC construction Feb. 9, 2017.
(Photo by Justin Hayworth/Grinnell College)

Saturday work at HSSC will continue for steel erection/detail and wall framing/sheathing. All major work activity at the Humanities and Social Studies Complex (HSSC) and the Admission and Financial Aid (AFA) building is included below. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit.

HSSC: Major activity week of Feb. 26

  • Continuation steel detail work (all areas)
  • Interior framing north pavilion 3rd floor
  • Window blocking (as needed)
  • Wall backing/blocking south pavilion 3rd floor
  • Door frames/backing south/north pavilion 3rd floor
  • Roofing north pavilion resume
  • Air barrier detail/spray (as needed)
  • Atrium fascia complete
  • Atrium soffit decking
  • Segmented curtain wall install
  • South pavilion curtain wall
  • Clerestory frame completion/glass install
  • Halo light gauge framing
  • 3rd floor MEP OH south pavilion
  • 3rd floor south pavilion framing
  • Electrical/plumbing OH south pavilion 2nd and 3rd floors
  • Basement MEP continuation
  • Masonry east elevation south pavilion
  • South pavilion stairs completion
  • South pavilion drywall 2nd floor start
  • South pavilion 1st floor (tentative) tape

AFA: Major activity week of Feb. 26

  • Fireplace CMU completes
  • Metal roof decking completes
  • Wood blocking at fascia continues
  • Erect waiting room steel
  • Overhead ductwork at 1st floor complete
  • Priority walls on 2nd floor framing
  • Gable wall framing complete
  • Start of spray on vapor barrier
  • Start plumbing piping racks overhead