Campus Construction Update: Aug. 20–26

All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO –thermoplastic polyolefin (membrane)

HSSC: Major activity week of Aug. 20

  • Basement MEP startup preparation
  • Insulation – duct/pipe north pavilion
  • Hang drywall – 3rd floor north pavilion/skylight south pavilion
  • Drywall finish – north pavilion 2nd and 3rd/skylight south pavilion
  • Paint – 2nd floor north pavilion
  • Ceiling pads – south pavilion 3rd floor
  • Ceiling grid – north pavilion 1st floor
  • Ceiling pads – north pavilion 1st floor
  • Chilled Beams – north pavilion 2nd and 3rd floors
  • Carpet/LVT – south pavilion 3rd floor
  • Carpet/LVT – north pavilion 1st floor
  • Overhead MEP – 3rd north pavilion
  • Spray foam – atrium high roof sheathing (as needed)
  • Atrium bridge ceiling framing
  • Restroom floor tile – north pavilion 1st and 2nd floor
  • Overhead MEP – 2nd/3rd floors north pavilion
  • Stone vestibules – north-south pavilion
  • Millwork south pavilion
  • Vestibule doors/frames

AFA: Major activity week of Aug. 20

  • Install ceiling tile, 2nd floor
  • Install light fixtures, 2nd floor
  • Install grilles, 2nd floor
  • Drop fire protection heads, 2nd floor
  • Drop fire protection heads, 1st floor
  • Paint door frames, 2nd floor
  • Install side light glass in HM frames, 2nd floor
  • Swinging wood doors, 2nd floor
  • Install Swiss pearl system
  • Install copper roof panels
  • Finish welding/decking/detailing of trellis structure
  • Install plumbing fixtures, 2nd floor

College Landscape Project: Major activity week of Aug. 20

  • Bench footings HSSC north side main plaza
  • Subgrade prep, HSSC main plaza
  • Gas line, AFA north
  • Sidewalk, AFA north
  • Concrete paving, AFA parking lot
  • Electrical rough-in, HSSC main plaza
  • Install bioswale north of HSSC

Leave a Reply

Your email address will not be published. Required fields are marked *