Campus Construction Update: Sept. 3–9

All major work activities for the Humanities and Social Studies Complex (HSSC), the Admission and Financial Aid (AFA) building, and campus landscaping are included. Abbreviation key: SOG — slab on grade; SOD — slab on deck; MEP — mechanical, electrical, and plumbing; FF — finished floor; HM — hollow metal; OH — overhead; AHU — air handling unit; any reference to “pour” refers to pouring concrete; CMU — concrete masonry unit; LVT – luxury vinyl tile (resilient flooring); TPO –thermoplastic polyolefin (membrane)

HSSC: Major activity week of Sept. 3

  • Basement MEP startups
  • Insulation – duct/pipe north pavilion
  • Hang drywall – 3rd floor north pavilion
  • Drywall finish – north pavilion 2nd and 3rd
  • Paint 2nd floor north pavilion
  • Ceiling grid – north pavilion 1st
  • Chilled beams – north pavilion 2nd and 3rd
  • Carpet/LVT – south pavilion 3rd floor
  • Lab casework install – south pavilion
  • Overhead MEP – 3rd north pavilion
  • Atrium bridge ceiling MEP
  • Atrium bridge – plaster
  • Restroom floor tile – north pavilion 2nd
  • Overhead MEP – 2nd/3rd north pavilion
  • Granite vestibules – south pavilion
  • Vestibule doors/frames
  • Doors and hardware – south pavilion
  • Framing/sheetrock 99% completed – south pavilion
  • Tape fire curtains – south pavilion
  • Lighting install – south pavilion 3rd, north pavilion 1st
  • Access flooring – south pavilion
  • Stoops footings/pads – south pavilion
  • Waldinger Utilities – Demobilize from site
  • Exterior east elevation eyebrow APC-4-atrium
  • Interior APC-5-atrium

AFA: Major activity week of Sept. 3

  • Wood door and hardware install on 2nd floor
  • Paint ongoing on 1st floor/bridge railing
  • Ceiling tile and grid install on 1st floor
  • Blocking and stud framing on trellis
  • Millwork delivery/install
  • Install Swiss Pearl System
  • Detail copper roof/soffit and fascia/gutters
  • Granite base install
  • TPO roofing install on trellis
  • Shade install
  • Wood door delivery and install for 1st floor
  • General clean

College Landscape Project: Major activity week of Sept. 3

  • Install light poles AFA east, south, Noyce n/s sidewalk
  • Electrical rough in HSSC main plaza
  • Install cove stone North 1/3 HSSC south courtyard
  • Subgrade prep HSSC main plaza
  • Underground rough in HSSC main plaza
  • Fine grade AFA south
  • Place concrete approach AFA south parking
  • Place sidewalk ramps AFA 8th and Park
  • Place curb/gutter AFA sw corner
  • Complete bioswale AFA west
  • Subgrade prep HSSC south courtyard